Project Overview
The Project "Construction of a new pier between Cargo pier to PEI fuel pier", consists the construction of a new 90m long pier which is meant to replace the existing pier due to its deteriorating status, which posed a danger. The project consists of driving 15m long type AZ26 sheet piles, there after casting of a new capping beam, installation of cathodic protection and all relevant elements required for the pier to become operational.
Main elements of the project
- Construction of a new pier in the length of 90mץ
- Supply and Driving of 15m long AZ26 sheet piles.
- Casting a new capping beam to -0.6 meter.
- Supply and installation of cathodic protection